ALBERTA, CANADA
The project is located in the largest industrial area in Western Canada, the Alberta Industrial Heartland.
Once operational the facility will annually divert 200k tonnes of waste away from landfill, generate 165 GWh of electricity and permanently capture and store 185k tonnes of CO2.
200,000t p.a.
waste
22
MWe
Under development
status
185,000t p.a.
CO2 CAPTURED
Incineration
WtE technology
2027
EXPECTED START OF operations
Birmingham, UK
The site is located in an industrial area outside of Birmingham, with planning permits for a Waste-to-Energy facility.
Once operational the facility will annually divert 150k tonnes of waste away from landfill, generate 165 GWh of electricity and permanently capture and store 195k tonnes of CO2.
150,000t p.a.
waste
22
MWE
Under development
Status
195,000t p.a.
C02 CAPTURED
Two-stage combustion
WtE technology
2027
Expected Start of operations
ALBERTA, CANADA
The project is located in the town of Innisfail in central Alberta.
Once operational the facility will annually divert 150k tonnes of waste away from landfill, generate 110 GWh of electricity and permanently capture and store 135k tonnes of CO2.
150,000t p.a.
waste
15
MWe
Under development
status
135,000t p.a.
CO2 CAPTURED
Incineration
WtE technology
2028
EXPECTED START OF operations